How to Use the Project Duration Estimator: Steps and a Worked Example
Estimate how many workdays a project will take. This guide shows what to enter, a worked example with real numbers, and the limits to keep in mind. The Project Duration Estimator tool is free, needs no account and runs in your browser.
What you need
- Total work (hours), for example 120
- Productive hours per workday, for example 6
Step by step
- Open the Project Duration Estimator tool.
- Fill in Total work (hours).
- Fill in Productive hours per workday.
- Read the result, which updates as soon as the inputs change.
Worked example
With these inputs:
- Total work (hours): 120
- Productive hours per workday: 6
the tool returns:
Estimated workdays: 20
A second example
Changing Total work (hours) 120 to 240 gives:
Estimated workdays: 40
Comparing two runs like this is a quick way to see how much each input moves the result.
How it works
The calculation is: Workdays = total work hours ÷ productive hours per day, rounded up. Enter the total work and productive hours per workday and the result appears straight away. Everything runs in your browser, so nothing you type is uploaded.
Things to keep in mind
Check your inputs, units and any local rules before you rely on the result.